CRX 50 Access pits constructed incorrectly
Access pits constructed incorrectly , unable to access entry points for airline or plate cables . We worked with what we had , site will make good as part of post works snags
see above
UU very happy with our resilience onsite to get the job done
Project management version control over our drawings
Kiri to update drawing register and provide whole company training
-