Projects / High Halden (Southern Water) ST-010476
High Halden (Southern Water) ST-010476
991 ACE Screener Pre-fabricated Package
Summary
Open To-dos
26
Overdue
26
Upcoming Schedule
0
Recent Messages
0
To-do Lists + To-dos
Delivery date:
Customer Contacts
• QS: · due 2024-10-11
• Project Manager: · due 2024-10-11
• Site Manager: · due 2024-10-11
Admin Tasks
• Upload Customer Requirements · due 2024-10-04
• Payment Terms · due 2024-10-04
• Handover · due 2024-10-04
• Payment · due 2024-12-20
• Warranty · due 2025-12-15
• Retention payment (date): · due 2025-12-15
Design
• Design Brief · due 2024-10-04
• Electrical Design · due 2024-10-14
• Design Contract Specific · due 2024-10-14
• Manual · due 2024-10-14
• Design General Assembly · due 2024-10-28
Contract Management Tasks.
• Client Confirmation · due 2024-10-04
• Initial Efacs Load · due 2024-10-07
• Pipework Efacs Load · due 2024-10-24
• Detail Efacs Load · due 2024-10-24
• Electrical Site Kit Load · due 2024-10-31
• Final Check and ensure all requirements are loaded..! · due 2024-11-21
• Manuals sent to client: · due 2024-12-02
• PIV Installation · due 2024-12-09
Purchasing
• Key Purchasing activities · due 2024-10-14
Re-Work to capture unplanned time and cost
Manufacturing
• Paint Spec · due 2024-10-21
• Sheet Metal · due 2024-11-04
• Rotating Build · due 2024-11-11
• Fabrication · due 2024-11-18
• Electrical Wiring · due 2024-12-02
• Mechanical Assembly · due 2024-12-02
• Overall Completion: · due 2024-12-02
Transport
• Define delivery lorry + lifting requirements · due 2024-12-09
Snags - Haigh Responsibility
Variation Orders / Additional Site Work
Photos
Miscellaneous Costs
Site Reports
Messages
No mirrored messages yet.
Schedule Entries
No mirrored schedule entries yet.
Documents
High Haldon Despatch Note.pdf
High Haldon RAMS 2025.pdf
High Halden Final Inspection Report.pdf
High Halden Screen and ace pump test cards.pdf
High Halden Lisep and Lipactor test cards..pdf
image006.png
image007.png
image008.png
image009.png
815300-01r1.pdf
815300-01r1.zip
OP10301-FQ-1 High Halden Stw - Series 991 ACE Screener Prefabricated Inlet.pdf
258 Order Definition Sheet High Halden Stw 06-09-2024.xls
124 High Halden Stw Contract Review Checklist 06-09-2024.doc
Recent Activity
High Haldon Despatch Note.pdf
High Haldon RAMS 2025.pdf
Electrical Site Kit Load
Electrical Site Kit Load
Contract Management Tasks.
Fabrication
Fabrication
Sheet Metal
Sheet Metal
Paint Spec
Paint Spec
Manufacturing
Electrical Wiring
Electrical Wiring
Mechanical Assembly
Mechanical Assembly
Rotating Build
Rotating Build
Overall Completion:
Overall Completion:
High Halden Final Inspection Report.pdf
Testing & Inspection
Testing & Inspection
High Halden Screen and ace pump test cards.pdf
High Halden Lisep and Lipactor test cards..pdf
image006.png
image007.png
image008.png
image009.png
Electrical Design
Electrical Design
Design
QS:
QS:
Customer Contacts
Project Manager:
Project Manager:
815300-01r1.pdf
815300-01r1.zip
Upload Customer Requirements
Upload Customer Requirements
Retention payment (date):
Retention payment (date):
Warranty
Warranty
Payment
Payment
Admin Tasks
OP10301-FQ-1 High Halden Stw - Series 991 ACE Screener Prefabricated Inlet.pdf
Payment Terms
Payment Terms
258 Order Definition Sheet High Halden Stw 06-09-2024.xls
Handover
Handover
124 High Halden Stw Contract Review Checklist 06-09-2024.doc
Customer Handover
Customer Handover
Manuals sent to client:
Manuals sent to client:
Installation and Commissioning
Installation and Commissioning
Card Table
No mirrored card-table items yet.
Sync History
No sync history yet.