Packaged Treatment Plant / Pump Station project
Summary
Open To-dos
65
Overdue
0
Upcoming Schedule
0
Recent Messages
0
To-do Lists + To-dos
Admin
• Quote
• Handover info for lead
• Planning Application
• Search before you dig
• Environment Agency - Application
• Deposit Payment, Invoice:
• Permission to connect to Storm Drain
• Final scope of works and sketches agreed with customer
Advanced Booking and Planning
• Order Pump Station
• Book Digger, Dumper & Fuel
• Order Ancillary Materials (pipework etc.)
• Book Ground-workers - Add Synchro ticket
• Make parts pack/Pick List
• Order Concrete, Gravel & Other Bulk
• Order Tanker - Jetter
• Order grab lorry/skip for spoil removal
On Site
• - Day 5, Engineers daily call
• - Day 4, Engineers daily call
• Signed RAMS
• 1) Call customer to check all is well
• Portaloo - OFF HIRE
• Update Tank Board once tank dispatched from Haigh or MPC
• Start Synchro ticket
• - Day 1, Customer courtesy call
Post Install
• Check payment of final bill, Invoice: - Commission certificate to be send to customer once final balance is paid
• Electrical Certificate
• Tank Warranty Certificate
• Snags
• Final email to ensure all has run well & Paperwork
• Post installation visit - within 3 months
• Advise customer tank service is due
• Waste Transfer Note(s) for any tankering
Messages
No mirrored messages yet.
Schedule Entries
No mirrored schedule entries yet.
Documents
Percolation Quotation HE.pdf
Recent Activity
Percolation Quotation HE.pdf
Quote
Quote
Admin
Order Portaloo
Order Portaloo
Order Telemetry - where applicable
Order Telemetry - where applicable
Order grab lorry/skip for spoil removal
Order grab lorry/skip for spoil removal
Order Tanker - Jetter
Order Tanker - Jetter
Order Pump Station
Order Pump Station
Order Treatment Tank - Add & allocate tank to Tank Board (if tank is located at Haigh) or Allocate tank to customer on Tank Board (if tank is located at MPC)
Order Treatment Tank - Add & allocate tank to Tank Board (if tank is located at Haigh) or Allocate tank to customer on Tank Board (if tank is located at MPC)
Order Concrete, Gravel & Other Bulk
Order Concrete, Gravel & Other Bulk
Make parts pack/Pick List
Make parts pack/Pick List
Order Ancillary Materials (pipework etc.)
Order Ancillary Materials (pipework etc.)
Book Digger, Dumper & Fuel
Book Digger, Dumper & Fuel
Check Sub-Contractors insurance (in date correct level of cover)
Check Sub-Contractors insurance (in date correct level of cover)
Book Ground-workers - Add Synchro ticket
Book Ground-workers - Add Synchro ticket
Advanced Booking and Planning
Book Electrician
Book Electrician
Reviewing all project aspects with lead engineer
Reviewing all project aspects with lead engineer
MPC Commissioning - ask Rob and arrange with Servicing team - if applicable
MPC Commissioning - ask Rob and arrange with Servicing team - if applicable
Accommodation
Accommodation
Handover info for lead
Handover info for lead
Deposit Payment, Invoice:
Deposit Payment, Invoice:
Final scope of works and sketches agreed with customer
Final scope of works and sketches agreed with customer
Search before you dig
Search before you dig
Permission to connect to Storm Drain
Permission to connect to Storm Drain
Section 106 application
Section 106 application
Section 50 application
Section 50 application
Environment Agency - Application
Environment Agency - Application
Planning Application
Planning Application
Levels Survey
Levels Survey
Date Confirmed with Customer -
Date Confirmed with Customer -
Introduction email and confirmed date
Introduction email and confirmed date
- Day 5, Engineers daily call
- Day 5, Engineers daily call
- Day 4, Engineers daily call
- Day 4, Engineers daily call
- Day 3, Engineers daily call
- Day 3, Engineers daily call
- Day 2, Engineers daily call
- Day 2, Engineers daily call
- Day 1, Engineers daily call
- Day 1, Engineers daily call
2) Call Chris B. & Andy Lowe to confirm everything is running smoothly
2) Call Chris B. & Andy Lowe to confirm everything is running smoothly
- Day 3, Customer courtesy call