Projects / Llansaint Wwtw S-081781, ST-010463
Llansaint Wwtw S-081781, ST-010463
New flow control system to fit existing 491 ACE Screener
Summary
Open To-dos
25
Overdue
24
Upcoming Schedule
0
Recent Messages
0
To-do Lists + To-dos
Delivery date:
Customer Contacts
• Site Manager · due 2024-02-15
• Project Manager · due 2024-02-15
• QS: · due 2024-02-16
Admin Tasks
• Payment Terms · due 2024-02-09
• Upload Customer Requirements · due 2024-02-12
• Handover · due 2024-02-12
• Payment · due 2024-04-26
• Warranty · due 2025-01-27
• Retention payment date: · due 2025-04-24
Design
• Manual · due 2024-02-19
• Electrical Design · due 2024-02-19
• Design Contract Specific · due 2024-02-19
• Design General Assembly · due 2024-03-08
• Design Brief
Contract Management Tasks
• Client Confirmation · due 2024-02-12
• Initial EFACs Load · due 2024-02-12
• Detailed EFACs Load · due 2024-02-21
• Final Check and ensure all requirements are loaded..! · due 2024-03-28
• Manuals sent to client: · due 2024-04-08
• Electrical Site Kit Load · due 2024-04-08
• Pipework EFACs Load · due 2024-04-08
• PIV Installation · due 2024-04-15
Purchasing
• Key Purchasing Activities · due 2024-02-19
Manufacturing
• Paint Spec · due 2024-02-26
• Sheet Metal · due 2024-03-15
• Rotating Build · due 2024-03-19
• Fabrication · due 2024-03-29
• Overall Completion: · due 2024-04-08
• Electrical Wiring · due 2024-04-12
• Mechanical Assembly · due 2024-04-12
Re-Work to capture unplanned time and cost
Transport
• Define lorry + lifting requirements · due 2024-04-15
Snags - Haigh Responsibility
Variation Orders / Additional Site Work
Site Reports
Photos
Miscellaneous Costs
Messages
No mirrored messages yet.
Schedule Entries
No mirrored schedule entries yet.
Documents
300880-01.pdf
FW_ OP9529_ Llansaint Stw - Retrofit Flow Control.msg
815145-01r1.pdf
815145-01r1.zip
Recent Activity
300880-01.pdf
Electrical Site Kit Load
Electrical Site Kit Load
Customer Handover
Customer Handover
Manuals sent to client:
Manuals sent to client:
Installation and Commissioning
Installation and Commissioning
RAMS / Crane Plans and Site Work
RAMS / Crane Plans and Site Work
PIV Installation
PIV Installation
Testing and QA
Testing and QA
Pipework EFACs Load
Pipework EFACs Load
Contract Management Tasks
Overall Completion:
Overall Completion:
Manufacturing
Electrical Wiring
Electrical Wiring
Mechanical Assembly
Mechanical Assembly
Rotating Build
Rotating Build
Paint Spec
Paint Spec
Sheet Metal
Sheet Metal
Fabrication
Fabrication
Upload Customer Requirements
Upload Customer Requirements
Warranty
Warranty
Payment
Payment
Admin Tasks
FW_ OP9529_ Llansaint Stw - Retrofit Flow Control.msg
Handover
Handover
Payment Terms
Payment Terms
815145-01r1.pdf
815145-01r1.zip
Retention payment date:
Retention payment date:
Design Contract Specific
Design Contract Specific
Manual
Manual
Electrical Design
Electrical Design
Design General Assembly
Design General Assembly
Design Brief
Design Brief
QS:
QS:
Snags - Haigh Responsibility
Design
Customer Contacts
Delivery date:
Final Check and ensure all requirements are loaded..!
Final Check and ensure all requirements are loaded..!
Client Confirmation
Client Confirmation
Card Table
No mirrored card-table items yet.
Sync History
No sync history yet.