Projects / Rainton FujiClean Install - CRX5 - Yorkshire Water
Rainton FujiClean Install - CRX5 - Yorkshire Water
Packaged Treatment Plant / Pump Station project
Summary
Open To-dos
54
Overdue
0
Upcoming Schedule
0
Recent Messages
0
To-do Lists + To-dos
Admin
• Project Cancelled
• Done - Survey / Site info
• Done - Quote
• Reviewing all project aspects with lead engineer
• MPC Commissioning - ask Rob and arrange with Servicing team - if applicable
• Accommodation
• Handover info for lead
• Search before you dig
Advanced Booking and Planning
• Done - Order Treatment Tank - Add & allocate tank to Tank Board (if tank is located at Haigh) or Allocate tank to customer on Tank Board (if tank is located at MPC)
• Order Ancillary Materials (pipework etc.)
• N/A - Order Concrete, Gravel & Other Bulk
• N/A - Order Tanker - Jetter
• N/A - Order grab lorry/skip for spoil removal
• N/A - Order Telemetry - where applicable
• N/A - Order Portaloo
• Done - Order Pump Station
On Site
• - Day 5, Engineers daily call
• - Day 4, Engineers daily call
• - Day 3, Engineers daily call
• Portaloo - OFF HIRE
• Client sign off
• Photos
• Digger & Dumper etc. OFF HIRE
• Signed RAMS
Post Install
• Tank Warranty Certificate
• Snags
• Final email to ensure all has run well & Paperwork
• Post installation visit - within 3 months
• Advise customer tank service is due
• Waste Transfer Note(s) for any tankering
• Final Email to Building Control - Declaration from client & principal contractor
• Engineers list - Stock Taken
Messages
No mirrored messages yet.
Schedule Entries
No mirrored schedule entries yet.
Documents
YW - Rainton WwTW (1) (1).docx
paint order top coat.docx
Rainton Fujiclean Trial.pptx
Rainton Fujiclean Trial.xlsx
Rainton Fujiclean HS2.xlsx
Rainton Flow 01-04-25.xlsx
Recent Activity
Project Cancelled
Project Cancelled
Admin
Done - Order Treatment Tank - Add & allocate tank to Tank Board (if tank is located at Haigh) or Allocate tank to customer on Tank Board (if tank is located at MPC)
Done - Order Treatment Tank - Add & allocate tank to Tank Board (if tank is located at Haigh) or Allocate tank to customer on Tank Board (if tank is located at MPC)
Advanced Booking and Planning
Order Ancillary Materials (pipework etc.)
Order Ancillary Materials (pipework etc.)
N/A - Order Concrete, Gravel & Other Bulk
N/A - Order Concrete, Gravel & Other Bulk
N/A - Order Tanker - Jetter
N/A - Order Tanker - Jetter
N/A - Order grab lorry/skip for spoil removal
N/A - Order grab lorry/skip for spoil removal
N/A - Order Telemetry - where applicable
N/A - Order Telemetry - where applicable
N/A - Order Portaloo
N/A - Order Portaloo
Done - Order Pump Station
Done - Order Pump Station
Done - Survey / Site info
Done - Survey / Site info
Done - Quote
Done - Quote
YW - Rainton WwTW (1) (1).docx
paint order top coat.docx
Book Digger, Dumper & Fuel
Book Digger, Dumper & Fuel
Make parts pack/Pick List
Make parts pack/Pick List
Book Electrician
Book Electrician
Check Sub-Contractors insurance (in date correct level of cover)
Check Sub-Contractors insurance (in date correct level of cover)
Accommodation
Accommodation
Reviewing all project aspects with lead engineer
Reviewing all project aspects with lead engineer
MPC Commissioning - ask Rob and arrange with Servicing team - if applicable
MPC Commissioning - ask Rob and arrange with Servicing team - if applicable
Search before you dig
Search before you dig
Handover info for lead
Handover info for lead
Deposit Payment, Invoice:
Deposit Payment, Invoice:
Final scope of works and sketches agreed with customer
Final scope of works and sketches agreed with customer
Permission to connect to Storm Drain
Permission to connect to Storm Drain
Section 106 application
Section 106 application
Section 50 application
Section 50 application
Planning Application
Planning Application
Environment Agency - Application
Environment Agency - Application
Building Control
Building Control
Rainton Fujiclean Trial.pptx
Rainton Fujiclean Trial.xlsx
Rainton Fujiclean HS2.xlsx
Rainton Flow 01-04-25.xlsx
Book Ground-workers - Add Synchro ticket
Book Ground-workers - Add Synchro ticket
Levels Survey
Levels Survey
Introduction email and confirmed date
Introduction email and confirmed date
- Day 5, Engineers daily call
- Day 5, Engineers daily call
Card Table
No mirrored card-table items yet.
Sync History
No sync history yet.