Projects / Sheldon Davies, Bowling Alley Cottage, Bowling Alley Lane, Marston Montgomery, Ashbourne, DE6 2FE - benandinca@btinternet.com - 07795454919

Sheldon Davies, Bowling Alley Cottage, Bowling Alley Lane, Marston Montgomery, Ashbourne, DE6 2FE - benandinca@btinternet.com - 07795454919

Packaged Treatment Plant / Pump Station project

Status: Active·Sync: Attention·Last synced: 2026-04-13 17:33·Last activity: 2025-09-30 10:09
Summary
Open To-dos
47
Overdue
4
Upcoming Schedule
0
Recent Messages
0
To-do Lists + To-dos

Admin

Open

• N/A Waste Transfer Note(s) for any tankering
• DONE - Signed RAMS
• N/A Accommodation
• DONE - Buildings Control
• DONE - Search before you dig
• DONE - Final scope of works and sketches agreed with customer
• N/A Permission to connect to Storm Drain
• N/A Environment Agency - Application
+ 8 more

Advanced Booking and Planning

Open

• N/A Order Portaloo
• N/A Order Control Panel - Telemetry - where applicable
• N/A Order grab lorry/skip for spoil removal
• N/A Order Tanker - Jetter
• N/A Order Concrete, Gravel & Other Bulk
• N/A Make parts pack/Pick List
• N/A Order Ancillary Materials (pipework etc.)
• N/A Book Digger, Dumper & Fuel
+ 4 more

On Site

Open

• DONE - Buildings Control Visit
• DONE - Call customer to check all is well - day one, day three and last day for final call
• N/A Portaloo - OFF HIRE
• N/A - Digger & Dumper etc. OFF HIRE
• DONE - Photos
• DONE - Client sign off

Post Install

Open

• Final Email to Building Control - Received final sign off and sent to Sheldon · due 2024-12-06
• PAID 03/12/24 - Check payment of final bill · due 2024-12-06
• DONE - Post installation visit - within 3 months - Dean to carry out post install checks on 18/12/24 · due 2025-01-01
• Done - Advise customer tank service is due · due 2025-10-01
• DONE - Commission Certificate - Sent to Sheldon 03/12/24
• DONE - Final email to ensure all has run well & Paperwork
• N/A Tank Warranty Certificate
• DONE - Service paperwork
+ 5 more
Messages
No mirrored messages yet.
Schedule Entries
No mirrored schedule entries yet.
Documents

24-120147 Final Certificate (April 2024) (1).pdf

Document · Louise Prince

Commission Certificate - Sheldon Davies.pdf

Document · Louise Prince

Commission Certificate - Sheldon Davies.docx

Document · Louise Prince

24-120147 Final Inspection Declaration Statements.docx

Document · Louise Prince

SSC - MPC - Sheldon Davies.pdf

Document · Louise Prince

Completion paperwork - DE6 2FE.msg

Document · Louise Prince

Fw_ Ref_ 24-120147 Bowling Alley Cottage_ Marston Montgomery_ Ashbourne_ DE6 2FE_ Site Inspection Report.msg

Document · Louise Prince

SSC - MPC - Sheldon Davies.pdf

Document · Louise Prince

SSC - MPC - Sheldon Davies.docx

Document · Louise Prince

DE62FE_1-Bowling-Alley-Cottages_MWC182C_30532871.pdf

Document · Louise Prince

Invoice INV-1309.pdf

Document · Louise Prince

WhatsApp Image 2024-11-08 at 08.31.56_d4065ad4.jpg

Document · Louise Prince

WhatsApp Image 2024-11-08 at 08.31.56_36247814.jpg

Document · Louise Prince

IMG-20241101-WA0003.jpg

Document · Louise Prince

IMG-20241101-WA0004.jpg

Document · Louise Prince

IMG-20241101-WA0005.jpg

Document · Louise Prince

IMG-20241101-WA0006.jpg

Document · Louise Prince

IMG-20241101-WA0007.jpg

Document · Louise Prince

IMG-20241101-WA0008.jpg

Document · Louise Prince

IMG-20241028-WA0030.jpg

Document · Louise Prince

IMG-20241028-WA0031.jpg

Document · Louise Prince

IMG-20241028-WA0032.jpg

Document · Louise Prince

IMG-20241028-WA0033.jpg

Document · Louise Prince

IMG-20241030-WA0006.jpg

Document · Louise Prince

IMG-20241030-WA0007.jpg

Document · Louise Prince

Recent Activity
Done - Advise customer tank service is due
2025-09-30 10:09 · Todo
Done - Advise customer tank service is due
Post Install
2025-09-30 10:09 · Todolist
DONE - Post installation visit - within 3 months - Dean to carry out post install checks on 18/12/24
2024-12-18 08:56 · Todo
DONE - Post installation visit - within 3 months - Dean to carry out post install checks on 18/12/24
Final Email to Building Control - Received final sign off and sent to Sheldon
2024-12-05 16:53 · Todo
Final Email to Building Control - Received final sign off and sent to Sheldon
24-120147 Final Certificate (April 2024) (1).pdf
2024-12-05 16:49 · Louise Prince · Document
DONE - Commission Certificate - Sent to Sheldon 03/12/24
2024-12-03 09:30 · Todo
DONE - Commission Certificate - Sent to Sheldon 03/12/24
Commission Certificate - Sheldon Davies.pdf
2024-12-03 09:28 · Louise Prince · Document
Commission Certificate - Sheldon Davies.docx
2024-12-03 09:28 · Louise Prince · Document
PAID 03/12/24 - Check payment of final bill
2024-12-03 09:10 · Todo
PAID 03/12/24 - Check payment of final bill
24-120147 Final Inspection Declaration Statements.docx
2024-12-03 08:44 · Louise Prince · Document
SSC - MPC - Sheldon Davies.pdf
2024-12-03 08:43 · Louise Prince · Document
N/A Order Portaloo
2024-11-29 16:33 · Todo
N/A Order Portaloo
Advanced Booking and Planning
2024-11-29 16:33 · Todolist
N/A Order Control Panel - Telemetry - where applicable
2024-11-29 16:33 · Todo
N/A Order Control Panel - Telemetry - where applicable
N/A Order grab lorry/skip for spoil removal
2024-11-29 16:33 · Todo
N/A Order grab lorry/skip for spoil removal
N/A Order Tanker - Jetter
2024-11-29 16:33 · Todo
N/A Order Tanker - Jetter
N/A Order Concrete, Gravel & Other Bulk
2024-11-29 16:33 · Todo
N/A Order Concrete, Gravel & Other Bulk
N/A Make parts pack/Pick List
2024-11-29 16:33 · Todo
N/A Make parts pack/Pick List
N/A Order Ancillary Materials (pipework etc.)
2024-11-29 16:33 · Todo
N/A Order Ancillary Materials (pipework etc.)
N/A Book Digger, Dumper & Fuel
2024-11-29 16:33 · Todo
N/A Book Digger, Dumper & Fuel
N/A Waste Transfer Note(s) for any tankering
2024-11-29 16:33 · Todo
N/A Waste Transfer Note(s) for any tankering
Admin
2024-11-29 16:33 · Todolist
DONE - Check Sub-Contractors insurance (in date correct level of cover)
2024-11-29 16:32 · Todo
DONE - Check Sub-Contractors insurance (in date correct level of cover)
DONE - Buildings Control Visit
2024-11-29 16:32 · Todo
DONE - Buildings Control Visit
On Site
2024-11-29 16:32 · Todolist
DONE - Call customer to check all is well - day one, day three and last day for final call
2024-11-29 16:32 · Todo
DONE - Call customer to check all is well - day one, day three and last day for final call
N/A Portaloo - OFF HIRE
2024-11-29 16:32 · Todo
N/A Portaloo - OFF HIRE
DONE - Final email to ensure all has run well & Paperwork
2024-11-29 16:31 · Todo
DONE - Final email to ensure all has run well & Paperwork
Completion paperwork - DE6 2FE.msg
2024-11-29 16:31 · Louise Prince · Document
Fw_ Ref_ 24-120147 Bowling Alley Cottage_ Marston Montgomery_ Ashbourne_ DE6 2FE_ Site Inspection Report.msg
2024-11-29 10:09 · Louise Prince · Document
N/A Tank Warranty Certificate
2024-11-29 10:08 · Todo
N/A Tank Warranty Certificate
DONE - Service paperwork
2024-11-29 10:08 · Todo
DONE - Service paperwork
SSC - MPC - Sheldon Davies.pdf
2024-11-29 10:08 · Louise Prince · Document
SSC - MPC - Sheldon Davies.docx
2024-11-29 10:08 · Louise Prince · Document
DONE - Electrical Certificate
2024-11-14 09:25 · Todo
DONE - Electrical Certificate
DE62FE_1-Bowling-Alley-Cottages_MWC182C_30532871.pdf
2024-11-14 09:24 · Louise Prince · Document
Invoice INV-1309.pdf
2024-11-14 09:24 · Louise Prince · Document
N/A - Digger & Dumper etc. OFF HIRE
2024-11-08 11:56 · Todo
N/A - Digger & Dumper etc. OFF HIRE
DONE - Photos
2024-11-08 11:56 · Todo
DONE - Photos
WhatsApp Image 2024-11-08 at 08.31.56_d4065ad4.jpg
2024-11-08 11:54 · Louise Prince · Document
Card Table
No mirrored card-table items yet.
Sync History
No sync history yet.