Project Activity

Cross-project Basecamp activity feed for operational visibility.

Sync Admin
2021-04-27 15:00 · Todo
Final email to ensure all has run well & Paperwork
2021-04-26 08:33 · Todo
DONE Concrete (Erewash) Gravel & Other Bulk (Travis Perkins)
2021-04-14 18:30 · Todo
Book Ground-workers - Dean & Luke - 19th April 21 one day
2021-04-12 11:21 · Todo
DONE Order Treatment Tank / Pump Station etc (cesspool ordered HIAB del 15.04.21)
2021-03-31 16:59 · Todo
DONE Book Digger, Dumper & Fuel - digger only
2021-03-03 17:33 · Todo
N/A - Permission to connect to Storm Drain
2021-03-03 17:23 · Todo
Order Control Panel - Telemetry - where applicable
2021-03-03 17:23 · Todo
Final scope of works and sketches agreed with customer
2021-03-03 17:23 · Todo
End of job call to installation lead / Improvement Review