2026-02-27 13:04 · Todo
Advise customer tank service is due
2025-12-04 12:27 · Todo
Post installation visit - within 3 months
2025-10-28 09:43 · Ruby Birks · Document
2025-10-28 09:43 · Helen · Document
2025-10-28 09:43 · Helen · Document
2025-10-23 09:54 · Todo
Done - Update Tank Board as complete once final payment received
2025-10-23 09:53 · Todo
Done - Validate & complete Synchro ticket
2025-10-23 09:52 · Todo
Done - Call Chris B. & Andy Lowe to confirm everything is running smoothly
2025-10-23 09:52 · Todo
1) Call customer to check all is well
2025-10-23 09:52 · Todo
N/A - Permission to connect to Storm Drain
2025-10-23 09:52 · Todo
N/A - Environment Agency - Application
Madeline Silence - STP Install - The Chapel, Manchester Rd, Hollingworth, Hyde SK14 8LA, UK - madeline.sillence@turntown.co.uk - 07879 621333 · Done - Building Control - Application payment made on 05/09/2025 - Site visit booked 12/09
2025-10-23 09:52 · Todo
Done - Building Control - Application payment made on 05/09/2025 - Site visit booked 12/09
2025-10-23 09:52 · Todo
Done - Reviewing all project aspects with lead engineer
2025-10-23 09:52 · Todo
Done - MPC Commissioning - ask Rob and arrange with Servicing team - if applicable
2025-10-23 09:52 · Todo
Done - Deposit Payment, Invoice: ST-34140
2025-10-23 09:52 · Todo
Done - Final scope of works and sketches agreed with customer
2025-10-22 08:48 · Todo
Done - Check payment of final bill
2025-10-22 08:48 · Todo
DONE - Commission Certificate - to be retained until final balance is paid.
2025-10-22 08:48 · Todo
Done - Final email to ensure all has run well & Paperwork
2025-10-22 08:47 · Todo
Done - Final Email to Building Control - Declaration from client & principal contractor
2025-10-15 16:49 · Helen · Document
2025-10-15 16:49 · Helen · Document
2025-10-08 10:23 · Todo
N/A - Order Telemetry - where applicable
2025-10-08 10:23 · Todo
N/A on Plant - Book Digger, Dumper & Fuel
2025-10-08 10:23 · Todo
Done - Order skip for spoil removal
Madeline Silence - STP Install - The Chapel, Manchester Rd, Hollingworth, Hyde SK14 8LA, UK - madeline.sillence@turntown.co.uk - 07879 621333 · Done - Order Treatment Tank - Added tank to TTB - Marsh Industries - PO005564 - Delivery Monday 08/09/2025
2025-10-08 10:23 · Todo
Done - Order Treatment Tank - Added tank to TTB - Marsh Industries - PO005564 - Delivery Monday 08/09/2025
2025-10-08 10:23 · Todo
Done - Order Concrete, Gravel & Other Bulk
2025-10-08 10:23 · Todo
☑ Make parts pack/Pick List - Handed over to Michael on 29/08/2025
2025-10-08 10:23 · Todo
Order Ancillary Materials (pipework etc.)
2025-10-03 09:25 · Nikoleta Gouzopoulou · Document
2025-10-03 09:25 · Nikoleta Gouzopoulou · Document
2025-10-03 09:25 · Nikoleta Gouzopoulou · Document
2025-10-03 09:25 · Nikoleta Gouzopoulou · Document
2025-10-03 09:25 · Nikoleta Gouzopoulou · Document
2025-10-03 09:25 · Nikoleta Gouzopoulou · Document
2025-10-03 09:25 · Nikoleta Gouzopoulou · Document
2025-10-03 09:25 · Nikoleta Gouzopoulou · Document
2025-10-03 09:25 · Nikoleta Gouzopoulou · Document
2025-10-03 09:25 · Nikoleta Gouzopoulou · Document
2025-10-03 09:25 · Nikoleta Gouzopoulou · Document
2025-10-03 09:25 · Nikoleta Gouzopoulou · Document
2025-10-03 09:25 · Nikoleta Gouzopoulou · Document
2025-09-22 13:06 · Todo
Done - Digger & Dumper etc. OFF HIRE
2025-09-22 11:42 · Todo
☑ Tank Warranty Certificate - Received 29/08/2025
2025-09-17 09:23 · Todo
End of job call to installation lead / Improvement Review
2025-09-11 11:22 · Todo
Done - Book Ground-workers - Add Synchro ticket
2025-09-11 11:03 · Todo
Done - Update Tank Board once tank dispatched
2025-09-01 13:07 · Todo
Done - Check Sub-Contractors insurance (in date correct level of cover)
2025-08-28 14:17 · Todo
Done - Introduction email and confirmed date
2025-08-28 14:14 · Todo
Waste Transfer Note(s) for any tankering