2022-12-13 15:30 · Todo
Advise customer tank service is due
2022-12-13 15:30 · Todo
Post installation visit - within 3 months
2022-12-13 15:30 · Todo
DONE Order Concrete, Gravel & Other Bulk (quote requested)
2022-12-13 15:30 · Todo
DONE Search before you dig (request submitted)
2021-06-08 06:09 · Todo
Final email to ensure all has run well & Paperwork
2021-05-26 12:31 · Kaz Lumb · Document
2021-05-06 18:55 · Todo
DONE - Order Treatment Tank / Pump Station etc
2021-04-29 10:52 · Michelle · Document
2021-04-29 10:52 · Michelle · Document
2021-04-29 10:34 · Michelle · Document
2021-04-29 10:34 · Michelle · Document
2021-04-27 10:25 · Todo
NA Digger & Dumper etc. OFF HIRE
2021-04-23 13:52 · Todo
DONE Order Ancillary Materials (pipework etc.)
2021-04-22 09:19 · Todo
Final scope of works and sketches agreed with customer
2021-04-21 16:33 · Todo
Introduction email and confirmed date
2021-04-21 11:53 · Todo
N/A - Book Digger, Dumper & Fuel (cust using own plant)
2021-04-20 12:54 · Kaz Lumb · Document
2021-04-20 12:54 · Kaz Lumb · Document
2021-04-19 16:46 · Todo
DONE - Book Ground-workers (Dean plus their man 5th and 6th May
2021-04-19 16:44 · Todo
N/A - Permission to connect to Storm Drain
2021-04-19 16:44 · Todo
N/A - Environment Agency - Application
2021-03-15 13:25 · Todo
Pre-start site visit to agree final scope of works - Dean booked for 6th April 2021
2021-03-15 12:32 · Todo
Order Control Panel - Telemetry - where applicable
2021-03-15 12:32 · Todo
Order grab lorry/skip for spoil removal
2021-03-15 12:32 · Todo
End of job call to installation lead / Improvement Review