Neil Timmins - STP Install - 1 Brampton Bridge, Clunbury, Craven Arms SY7 0HQ, UK - neil.timmins@outlook.com - 07484 748557 · Done - Final Email to Building Control - Declaration from client & principal contractor
2026-03-06 14:49 · Todo
Done - Final Email to Building Control - Declaration from client & principal contractor
2026-03-06 14:49 · Ruby Birks · Document
2026-02-27 13:04 · Todo
Advise customer tank service is due
2025-12-04 12:35 · Todo
Post installation visit - within 3 months
2025-11-12 10:43 · Todo
Done - Update Tank Board as complete once final payment received
2025-11-12 10:43 · Todo
Done - Check final invoice paid - Invoice: and sent commissioning certificate
2025-11-12 10:43 · Todo
Done - Send completion paperwork
2025-11-12 10:42 · Todo
DONE - Commission Certificate - to be retained until final balance is paid.
2025-11-12 10:42 · Todo
N/A - Digger & Dumper etc. OFF HIRE
2025-11-12 10:42 · Todo
Call customer to check all is well
2025-11-12 10:42 · Todo
Done - Date TBC - Portaloo - OFF HIRE
2025-11-12 10:42 · Todo
N/A - Permission to connect to Storm Drain
2025-11-12 10:42 · Todo
N/A - Section 106 application
2025-11-12 10:42 · Todo
N/A - Environment Agency - Application
2025-11-12 10:42 · Todo
N/A - Section 50 application
2025-11-12 10:42 · Todo
Done - Building Control Commencement of Works
2025-11-12 10:42 · Todo
Done - Final scope of works and RAMS sent and agreed with customer
2025-11-12 10:42 · Todo
Done - Final scope of works
2025-11-12 10:42 · Todo
Done - Reviewing all project aspects with lead engineer
2025-11-12 10:42 · Todo
Done - Handover info for lead
2025-11-12 10:42 · Todo
Done - Deposit Payment, Invoice: ST-34516
2025-11-12 10:42 · Todo
Done - Search before you dig
2025-11-06 14:49 · Todo
Done - Electrical Certificate
2025-11-06 14:48 · Ruby Birks · Document
2025-10-14 10:20 · Helen · Document
2025-10-14 10:20 · Helen · Document
2025-10-14 10:19 · Helen · Document
2025-10-14 10:19 · Helen · Document
2025-10-14 09:40 · Todo
Done - Tank Warranty Certificate
2025-10-14 09:40 · Ruby Birks · Document
2025-10-14 09:40 · Ruby Birks · Document
2025-10-08 11:11 · Todo
Scheduled - Follow Up Visit
2025-10-08 11:10 · Todo
N/A - Waste Transfer Note(s) for any tankering
2025-10-08 11:10 · Todo
End of job call to installation lead / Improvement Review
2025-10-08 11:10 · Todo
Engineers list - Stock Taken
2025-09-29 12:18 · Todo
N/A - Order Telemetry - where applicable
2025-09-29 12:18 · Todo
N/A - Order grab lorry/skip for spoil removal
2025-09-29 12:18 · Todo
N/A - Order Tanker - Jetter
2025-09-29 12:18 · Todo
N/A - Book Digger, Dumper & Fuel
2025-09-29 12:18 · Todo
N/A - Order Concrete, Gravel & Other Bulk
2025-09-29 12:18 · Todo
N/A - Order Ancillary Materials (pipework etc.)
2025-09-29 12:18 · Todo
N/A - Make parts pack/Pick List
2025-09-29 12:18 · Todo
Done - Order Treatment Tank - Add to TTB
2025-09-25 16:16 · Ruby Birks · Document
2025-09-25 16:16 · Ruby Birks · Document
2025-09-25 15:40 · Ruby Birks · Document
2025-09-25 14:39 · Todo
Booked - Buildings Control Visit
2025-09-25 12:34 · Todo
Done - Introduction email and CUSTOMER CONFIRMED DATE 1st-3rd Oct
2025-09-25 11:28 · Ruby Birks · Document
2025-09-24 14:32 · Todo
- Day 5, Engineers daily call
2025-09-24 14:32 · Todo
- Day 4, Engineers daily call
2025-09-24 14:31 · Todo
- Day 3, Engineers daily call
2025-09-24 14:31 · Todo
- Day 2, Engineers daily call
2025-09-24 14:31 · Todo
- Day 1, Engineers daily call
2025-09-24 14:31 · Todo
- Day 3, Customer courtesy call
2025-09-24 14:31 · Todo
- Day 1, Customer courtesy call
2025-09-24 14:07 · Todo
Done - Book Ground-workers - Add Synchro ticket
2025-08-28 14:42 · Todo
Check Sub-Contractors insurance (in date correct level of cover)
2025-08-28 14:42 · Todo
Validate & complete Synchro ticket