Project Activity

Cross-project Basecamp activity feed for operational visibility.

Sync Admin
2026-01-06 09:34 · Todo
No Reply letter sent Advise customer tank service is due
2025-01-24 12:58 · Todo
Engineers list - Stock Taken
2025-01-24 12:25 · Todo
Digger & Dumper etc. OFF HIRE
2025-01-24 12:24 · Todo
Final scope of works and sketches agreed with customer
2024-10-28 15:26 · Todo
Final email to ensure all has run well & Paperwork
2024-06-14 15:03 · Todo
Post installation visit - within 3 months
Peter Bickmore - The Old Rectory, Orchard Row, Icomb, Cheltenham GL54 1JB peter@icombrectory.co.uk 07860 964545 · Post installation check - The Old Rectory_ Orchard Row_ Icomb_ Cheltenham GL54 1JB - FujiClean CEN5.msg
2024-06-14 15:02 · Louise Prince · Document
2024-05-24 16:52 · Louise Prince · Document
2024-05-24 16:52 · Todo
Commission Certificate - to be retained until final balance is paid.
2024-05-24 16:52 · Louise Prince · Document
2024-05-15 14:31 · Todo
Check payment of final bill
2024-04-17 11:18 · Todo
DONE Order Treatment Tank / Pump Station etc
2024-04-16 10:38 · Louise Prince · Document
2024-04-16 10:38 · Louise Prince · Document
2024-04-16 10:38 · Louise Prince · Document
2024-04-16 10:38 · Louise Prince · Document
2024-04-11 10:15 · Louise Prince · Document
2024-03-28 17:01 · Louise Prince · Document
2024-03-28 17:01 · Louise Prince · Document
2024-03-20 15:31 · Kirsty Mosley · Document
2024-03-20 15:31 · Kirsty Mosley · Document
2024-03-20 15:31 · Kirsty Mosley · Document
2024-03-20 15:31 · Kirsty Mosley · Document
2024-03-20 15:31 · Kirsty Mosley · Document
2024-03-20 15:31 · Kirsty Mosley · Document
2024-03-20 15:30 · Todo
DONE Order Concrete, Gravel & Other Bulk
2024-03-20 15:30 · Kirsty Mosley · Document
2024-03-13 15:39 · Kirsty Mosley · Document
2024-03-13 15:39 · Kirsty Mosley · Document
2024-03-13 15:39 · Kirsty Mosley · Document
2024-03-13 15:39 · Kirsty Mosley · Document
2024-03-13 15:39 · Kirsty Mosley · Document
2024-03-13 15:39 · Kirsty Mosley · Document
2024-03-13 15:35 · Kirsty Mosley · Document
2024-03-13 15:35 · Kirsty Mosley · Document
2024-03-13 15:35 · Kirsty Mosley · Document
2024-03-13 15:35 · Kirsty Mosley · Document
2024-03-13 15:15 · Todo
DONE Order Tanker - Jetter
2024-03-13 14:57 · Todo
DONE Book Digger, Dumper & Fuel
2024-03-13 14:52 · Todo
DONE Book Ground-workers
2024-03-13 14:17 · Todo
Tank Warranty Certificate
2024-03-13 13:56 · Kirsty Mosley · Document
2024-03-13 13:56 · Kirsty Mosley · Document
2024-03-13 13:56 · Kirsty Mosley · Document
2024-03-13 13:56 · Kirsty Mosley · Document
2024-03-13 13:56 · Kirsty Mosley · Document
2024-03-13 13:56 · Kirsty Mosley · Document
2024-03-13 13:56 · Kirsty Mosley · Document
2024-03-13 13:56 · Kirsty Mosley · Document
2024-03-13 13:56 · Kirsty Mosley · Document
2024-03-13 13:56 · Kirsty Mosley · Document
2024-03-13 13:56 · Kirsty Mosley · Document
2024-03-13 13:56 · Kirsty Mosley · Document
2024-03-13 13:51 · Kirsty Mosley · Document
2024-03-13 13:51 · Kirsty Mosley · Document
2024-03-13 13:49 · Todo
Introduction email and confirmed date
2024-03-13 13:18 · Todo
Order Control Panel - Telemetry - where applicable
2024-03-13 13:18 · Todo
Order grab lorry/skip for spoil removal
2024-03-13 13:18 · Todo
Make parts pack at Heanor
2024-03-13 13:18 · Todo
Order Ancillary Materials (pipework etc.)
2024-03-13 13:18 · Todo
Check Sub-Contractors insurance (in date correct level of cover)
2024-03-13 13:18 · Todo
Waste Transfer Note(s) for any tankering
2024-03-13 13:18 · Todo
Permission to connect to Storm Drain
2024-03-13 13:18 · Todo
Environment Agency - Application
2024-03-13 13:18 · Todo
Final Email to Building Control
Peter Bickmore - The Old Rectory, Orchard Row, Icomb, Cheltenham GL54 1JB peter@icombrectory.co.uk 07860 964545 · Call customer to check all is well - day one, day three and last day for final call
2024-03-13 13:18 · Todo
Call customer to check all is well - day one, day three and last day for final call
2024-03-13 13:18 · Todo
Buildings Control Visit
2024-03-13 13:17 · Todo
End of job call to installation lead / Improvement Review