2026-03-13 15:21 · Sophie McNaughton · Document
2026-03-13 14:37 · Sophie McNaughton · Document
2026-03-13 14:37 · Sophie McNaughton · Document
2026-03-13 13:55 · Todo
N/A - Building Control Visit
2026-03-13 13:54 · Todo
N/A - Arrange spoil removal
2026-03-13 13:54 · Todo
N/A - Order pump station (if needed)
2026-03-13 13:54 · Todo
N/A - Order aggregates - currently have credit notes with TP - USE
2026-03-13 13:53 · Todo
N/A - Order any additional materials
2026-03-13 13:53 · Todo
N/A - Arrange tank delivery if Fuji
2026-03-13 13:53 · Todo
N/A - Order tank - add to TTB
2026-03-13 13:53 · Todo
N/A - Print Completion Notice and Give to Engineer
2026-03-13 13:53 · Todo
N/A - Arrange Commissioning
2026-03-13 13:52 · Todo
N/A - Pre-Install documents sent to customer
2026-03-13 13:52 · Todo
N/A - EA Permit/Sections/Planning
2026-03-13 13:52 · Todo
N/A - Send Commencement Notice to Building Control
2026-03-13 13:52 · Todo
Done - Add to synchro and confirm insurance
2026-03-13 13:52 · Todo
Done - Introduction email to customer
2026-03-13 13:48 · Sophie McNaughton · Document
2026-03-13 13:47 · Sophie McNaughton · Document
2026-03-13 13:47 · Sophie McNaughton · Document
2026-03-13 13:47 · Sophie McNaughton · Document
2026-03-13 13:47 · Sophie McNaughton · Document
2026-03-13 13:47 · Sophie McNaughton · Document
2026-03-13 13:47 · Sophie McNaughton · Document
2026-03-13 13:47 · Todo
Call to Customer for Start of Works
2026-03-13 13:47 · Todo
Advise Customer Service is Due
2026-03-13 13:47 · Todo
Post-Install Visit - Within 3 Months
2026-03-13 13:47 · Todo
Update TTB Once Payment Received
2026-03-13 13:47 · Todo
Final Building Control Certificate
2026-03-13 13:47 · Todo
Signed Declaration Sent to Building Control