Project Activity

Cross-project Basecamp activity feed for operational visibility.

Sync Admin
2021-09-22 12:34 · Todo
Final email to ensure all has run well & Paperwork
2021-08-03 08:38 · Todo
Order Ancillary Materials (pipework etc.)
2021-07-19 14:17 · Todo
Order Treatment Tank / Pump Station etc
2021-07-08 14:32 · Todo
Final scope of works and sketches agreed with customer
2021-07-05 15:34 · Todo
Order Control Panel - Telemetry - where applicable
2021-07-05 15:34 · Todo
Order grab lorry/skip for spoil removal
2021-06-04 11:19 · Todo
Waste Transfer Note(s) for any tankering
2021-06-04 11:19 · Todo
Post installation visit - within 3 months
2021-06-04 11:19 · Todo
End of job call to installation lead / Improvement Review