Project Activity

Cross-project Basecamp activity feed for operational visibility.

Sync Admin
2025-01-31 13:12 · Todo
Final email to ensure all has run well & Paperwork
2025-01-31 13:12 · Todo
Final Email to Building Control
2025-01-31 13:12 · Todo
Digger & Dumper etc. OFF HIRE
2025-01-31 13:11 · Todo
Order grab lorry/skip for spoil removal
2025-01-31 13:11 · Todo
DONE Order Treatment Tank / Pump Station etc
2025-01-31 13:11 · Todo
DONE Order Concrete, Gravel & Other Bulk
2024-04-29 11:50 · Todo
Advise customer tank service is due - DONE 29/04/24
2024-04-29 11:49 · Todo
Post installation visit - within 3 months
2023-08-15 14:02 · Todo
DONE Book Digger, Dumper & Fuel
2023-03-21 10:22 · Kirsty Mosley · Document
2023-03-21 10:22 · Kirsty Mosley · Document
2023-03-21 10:22 · Kirsty Mosley · Document
2023-03-21 10:22 · Kirsty Mosley · Document
2023-03-21 10:22 · Kirsty Mosley · Document
2023-03-21 10:22 · Kirsty Mosley · Document
2023-03-21 10:15 · Kirsty Mosley · Document
2023-03-21 10:15 · Kirsty Mosley · Document
2023-03-20 18:25 · Kirsty Mosley · Document
2023-03-20 18:25 · Kirsty Mosley · Document
2023-03-20 18:25 · Kirsty Mosley · Document
2023-03-20 18:25 · Kirsty Mosley · Document
2023-03-20 18:25 · Kirsty Mosley · Document
2023-03-20 18:25 · Kirsty Mosley · Document
2023-03-20 18:25 · Kirsty Mosley · Document
2023-03-20 18:25 · Kirsty Mosley · Document
2023-03-20 18:25 · Kirsty Mosley · Document
2023-03-20 18:25 · Kirsty Mosley · Document
2023-03-20 18:25 · Kirsty Mosley · Document
2023-03-20 18:25 · Kirsty Mosley · Document
2023-03-20 18:25 · Kirsty Mosley · Document
2023-03-20 18:25 · Kirsty Mosley · Document
2023-03-20 18:25 · Kirsty Mosley · Document
2023-03-20 18:25 · Kirsty Mosley · Document
2023-03-20 18:25 · Kirsty Mosley · Document
2023-03-20 18:25 · Kirsty Mosley · Document
2023-03-20 18:25 · Kirsty Mosley · Document
2023-03-20 18:25 · Kirsty Mosley · Document
2023-03-20 18:25 · Kirsty Mosley · Document
2023-03-20 18:25 · Kirsty Mosley · Document
2023-03-20 18:25 · Kirsty Mosley · Document
2023-03-20 18:25 · Kirsty Mosley · Document
2023-03-20 18:18 · Kirsty Mosley · Document
2023-03-20 18:18 · Kirsty Mosley · Document
2023-03-16 15:02 · Todo
Permit to dig - in replacement of road closure
2023-03-02 20:25 · Todo
Final scope of works and sketches agreed with customer
2023-03-02 20:25 · Todo
Waste Transfer Note(s) for any tankering
2022-12-23 08:42 · Todo
Introduction email and confirmed date
2022-12-23 08:37 · Todo
Order Control Panel - Telemetry - where applicable
2022-12-23 08:37 · Todo
Order Ancillary Materials (pipework etc.)
2022-12-23 08:37 · Todo
Permission to connect to Storm Drain
2022-12-23 08:37 · Todo
Environment Agency - Application
2022-12-23 08:37 · Todo
End of job call to installation lead / Improvement Review