Project Activity

Cross-project Basecamp activity feed for operational visibility.

Sync Admin
2022-12-13 15:30 · Todo
Advise customer tank service is due
2022-12-13 15:30 · Todo
Post installation visit - within 3 months
2022-12-13 15:30 · Todo
Final email to ensure all has run well & Paperwork
2022-12-13 15:30 · Todo
Final Email to Building Control
2022-12-13 15:30 · Todo
Electrical Certificate
2022-12-13 15:30 · Todo
Digger & Dumper etc. OFF HIRE
2022-12-13 15:30 · Todo
DONE Book Electrician
2022-12-13 15:30 · Todo
Introduction email and confirmed date
2021-11-11 00:15 · Kaz Lumb · Document
2021-10-25 11:49 · Kaz Lumb · Document
2021-10-25 11:49 · Kaz Lumb · Document
2021-10-25 11:49 · Kaz Lumb · Document
2021-10-25 11:49 · Kaz Lumb · Document
2021-10-25 11:49 · Kaz Lumb · Document
2021-10-25 11:49 · Kaz Lumb · Document
2021-10-25 11:49 · Kaz Lumb · Document
2021-10-25 11:49 · Kaz Lumb · Document
2021-10-21 13:53 · Kaz Lumb · Document
2021-10-21 13:53 · Kaz Lumb · Document
2021-10-21 13:53 · Kaz Lumb · Document
2021-10-21 13:37 · Kaz Lumb · Document
2021-10-21 13:37 · Todo
Tank Warranty Certificate
2021-10-21 13:17 · Carly Krupiak · Document
2021-10-21 13:17 · Todo
Commission Certificate
2021-10-21 13:17 · Carly Krupiak · Document
2021-10-21 13:15 · Carly Krupiak · Document
2021-10-21 13:14 · Carly Krupiak · Document
2021-10-19 10:30 · Kaz Lumb · Document
2021-10-19 10:30 · Kaz Lumb · Document
2021-10-19 10:30 · Kaz Lumb · Document
2021-10-19 10:30 · Kaz Lumb · Document
2021-10-19 10:30 · Kaz Lumb · Document
2021-10-19 10:30 · Kaz Lumb · Document
2021-10-19 10:30 · Kaz Lumb · Document
2021-10-19 10:30 · Kaz Lumb · Document
2021-10-19 10:30 · Kaz Lumb · Document
2021-10-19 10:30 · Kaz Lumb · Document
2021-10-19 10:30 · Kaz Lumb · Document
2021-10-19 10:30 · Kaz Lumb · Document
2021-10-19 10:30 · Kaz Lumb · Document
2021-10-19 10:30 · Kaz Lumb · Document
2021-10-19 10:30 · Kaz Lumb · Document
2021-10-19 10:30 · Kaz Lumb · Document
2021-10-19 10:30 · Kaz Lumb · Document
2021-10-19 10:30 · Kaz Lumb · Document
2021-10-19 10:30 · Kaz Lumb · Document
2021-10-19 10:30 · Kaz Lumb · Document
2021-10-19 10:30 · Kaz Lumb · Document
2021-10-19 10:30 · Kaz Lumb · Document
2021-10-19 10:30 · Kaz Lumb · Document
2021-10-19 10:30 · Kaz Lumb · Document
2021-10-19 10:30 · Kaz Lumb · Document
2021-10-19 10:30 · Kaz Lumb · Document
2021-10-19 10:30 · Kaz Lumb · Document
2021-10-14 15:36 · Todo
TBC Order Concrete, Gravel & Other Bulk
2021-10-13 13:42 · Todo
Buildings Control Visit
2021-10-12 14:07 · Todo
Order Treatment Tank / Pump Station etc
2021-10-08 12:24 · Todo
DONE Book Digger, Dumper & Fuel
2021-10-08 11:31 · Todo
Final scope of works and sketches agreed with customer
2021-10-07 16:11 · Todo
Book Ground-workers
2021-10-05 09:59 · Todo
Search before you dig
2021-10-04 14:33 · Todo
NA Order grab lorry/skip for spoil removal
2021-09-30 08:36 · Todo
Tankering - turn septic tank to cess pool
2021-09-29 16:20 · Todo
NA Permission to connect to Storm Drain
2021-09-29 16:20 · Todo
NA Environment Agency - Application
2021-09-29 16:20 · Todo
NA Planning Application
2021-09-29 08:46 · Todo
NA Order Tanker - Jetter Dave to arrange
2021-09-22 13:08 · Todo
PERC TEST - RAMS, orders etc - Dean 20-21 Sept 2021
2021-09-22 08:43 · Todo
Waste Transfer Note(s) for any tankering
2021-08-20 13:13 · Todo
Order Control Panel - Telemetry - where applicable
2021-08-20 13:13 · Todo
Make parts pack at Heanor
2021-08-20 13:13 · Todo
Order Ancillary Materials (pipework etc.)
2021-08-20 13:13 · Todo
Payment of final bill
2021-08-20 13:13 · Todo
End of job call to installation lead / Improvement Review