Packaged Treatment Plant / Pump Station project

Status: Active·Sync: Attention·Last synced: 2026-04-13 17:27·Last activity: 2026-02-27 13:04
Summary
Open To-dos
63
Overdue
1
Upcoming Schedule
0
Recent Messages
0
To-do Lists + To-dos

Admin

Open

• N/A - Section 106 application
• N/A - Section 50 application
• Done - MPC Commissioning - ask Rob and arrange with Servicing team - if applicable
• Done - Accommodation
• Done - Handover info for lead
• N/A - Levels Survey
• Done - Reviewing all project aspects with lead engineer
• Done - Final scope of works and sketches agreed with customer
+ 10 more

Advanced Booking and Planning

Open

• N/A - Order Pump Station
• N/A - Order Ancillary Materials (pipework etc.)
• Done - Make parts pack/Pick List
• Done - Order Concrete, Gravel & Other Bulk
• Done - Order Treatment Tank - Add & allocate tank to Tank Board (if tank is located at Haigh) or Allocate tank to customer on Tank Board (if tank is located at MPC)
• Done - Order Tanker - Jetter
• Done - Order grab lorry/skip for spoil removal
• N/A - Order Telemetry - where applicable
+ 5 more

On Site

Open

• Done - Skip - OFF HIRE
• Client sign off
• Done - Day 1 Engineer check in
• Done - Digger & Dumper etc. OFF HIRE
• Done - Call Shaun/Crutch to confirm everything is running smoothly
• N/A - 1) Call customer to check all is well
• N/A - Portaloo - OFF HIRE
• Done - Day 3, Message Customer
+ 10 more

Post Install

Open

• Final Email to Building Control - Declaration from client & principal contractor - Pending client Declaration signage · due 2026-03-31
• ☑ Advise customer tank service is due - Installed w/c 11/08/2025 · due 2026-08-03
• Done - Tank Warranty Certificate
• ☑ Post installation visit - within 3 months - Installed w/c 11/08/2025
• Done - Top Soiling
• Done - Commission Certificate
• Paid - Check payment of final bill, Invoice: 34514
• Done - Snags
+ 10 more
Messages
No mirrored messages yet.
Schedule Entries
No mirrored schedule entries yet.
Documents

Screenshot 2026-01-19 130148.png

Document · Ruby Birks

Warranty 329255.pdf

Document · Ruby Birks

Pennine View Tank Warranty Form.pdf

Document · Ruby Birks

Screenshot 2025-11-12 101530.png

Document · Ruby Birks

Screenshot 2025-11-12 101524.png

Document · Ruby Birks

Screenshot 2025-11-12 101603.png

Document · Ruby Birks

WhatsApp Image 2025-10-23 at 09.50.33_b1363f00.jpg

Document · Ruby Birks

Screenshot 2025-10-23 090423.png

Document · Ruby Birks

Screenshot 2025-10-23 090319.png

Document · Ruby Birks

IMG-20251003-WA0007.jpg

Document · Ruby Birks

IMG-20251003-WA0008.jpg

Document · Ruby Birks

IMG-20251003-WA0009.jpg

Document · Ruby Birks

IMG-20251003-WA0010.jpg

Document · Ruby Birks

IMG-20251003-WA0011.jpg

Document · Ruby Birks

IMG-20250827-WA0001.jpg

Document · Nikoleta Gouzopoulou

IMG-20250827-WA0002.jpg

Document · Nikoleta Gouzopoulou

IMG-20250827-WA0003.jpg

Document · Nikoleta Gouzopoulou

IMG-20250827-WA0004.jpg

Document · Nikoleta Gouzopoulou

IMG-20250827-WA0005.jpg

Document · Nikoleta Gouzopoulou

IMG-20250827-WA0006.jpg

Document · Nikoleta Gouzopoulou

IMG-20250827-WA0007.jpg

Document · Nikoleta Gouzopoulou

IMG-20250827-WA0008.jpg

Document · Nikoleta Gouzopoulou

IMG-20250827-WA0009.jpg

Document · Nikoleta Gouzopoulou

IMG-20250827-WA0010.jpg

Document · Nikoleta Gouzopoulou

IMG-20250827-WA0012.jpg

Document · Nikoleta Gouzopoulou

Recent Activity
☑ Advise customer tank service is due - Installed w/c 11/08/2025
2026-02-27 13:04 · Todo
☑ Advise customer tank service is due - Installed w/c 11/08/2025
Post Install
2026-02-27 13:04 · Todolist
Final Email to Building Control - Declaration from client & principal contractor - Pending client Declaration signage
2026-02-27 12:58 · Todo
Final Email to Building Control - Declaration from client & principal contractor - Pending client Declaration signage
Screenshot 2026-01-19 130148.png
2026-01-19 13:02 · Ruby Birks · Document
Done - Tank Warranty Certificate
2025-11-14 12:11 · Todo
Done - Tank Warranty Certificate
Warranty 329255.pdf
2025-11-13 11:07 · Ruby Birks · Document
Pennine View Tank Warranty Form.pdf
2025-11-12 16:11 · Ruby Birks · Document
☑ Post installation visit - within 3 months - Installed w/c 11/08/2025
2025-11-12 10:18 · Todo
☑ Post installation visit - within 3 months - Installed w/c 11/08/2025
Screenshot 2025-11-12 101530.png
2025-11-12 10:16 · Ruby Birks · Document
Screenshot 2025-11-12 101524.png
2025-11-12 10:16 · Ruby Birks · Document
Screenshot 2025-11-12 101603.png
2025-11-12 10:16 · Ruby Birks · Document
Done - Top Soiling
2025-11-11 17:05 · Todo
Done - Top Soiling
Done - Commission Certificate
2025-11-07 10:53 · Todo
Done - Commission Certificate
Paid - Check payment of final bill, Invoice: 34514
2025-11-07 10:51 · Todo
Paid - Check payment of final bill, Invoice: 34514
Done - Snags
2025-11-07 10:51 · Todo
Done - Snags
Done - Engineer Invoice
2025-11-07 10:50 · Todo
Done - Engineer Invoice
☑ End of job call to installation lead / Improvement Review
2025-11-07 10:50 · Todo
☑ End of job call to installation lead / Improvement Review
☑ Customer Feedback
2025-11-07 10:50 · Todo
☑ Customer Feedback
☑ Update Tank Board as complete once final payment received
2025-11-07 10:50 · Todo
☑ Update Tank Board as complete once final payment received
Done - Final email to ensure all has run well & Paperwork - Sent 12/09/2025
2025-11-07 10:50 · Todo
Done - Final email to ensure all has run well & Paperwork - Sent 12/09/2025
Done - Validate & complete Synchro ticket
2025-11-07 10:50 · Todo
Done - Validate & complete Synchro ticket
N/A - Portaloo - OFF HIRE
2025-11-07 10:47 · Todo
N/A - Portaloo - OFF HIRE
N/A - 1) Call customer to check all is well
2025-11-07 10:47 · Todo
N/A - 1) Call customer to check all is well
Client sign off
2025-11-07 10:47 · Todo
Client sign off
Done - Day 1 Engineer check in
2025-11-07 10:47 · Todo
Done - Day 1 Engineer check in
Done - Call Shaun/Crutch to confirm everything is running smoothly
2025-11-07 10:47 · Todo
Done - Call Shaun/Crutch to confirm everything is running smoothly
Done - Day 3, Message Customer
2025-11-07 10:47 · Todo
Done - Day 3, Message Customer
Done - Day 1, Message Customer
2025-11-07 10:47 · Todo
Done - Day 1, Message Customer
Done - Skip - OFF HIRE
2025-11-07 10:47 · Todo
Done - Skip - OFF HIRE
Done - Digger & Dumper etc. OFF HIRE
2025-11-07 10:47 · Todo
Done - Digger & Dumper etc. OFF HIRE
On Site
2025-11-07 10:47 · Todolist
WhatsApp Image 2025-10-23 at 09.50.33_b1363f00.jpg
2025-10-23 09:51 · Ruby Birks · Document
Waste Transfer Note(s) for any tankering
2025-10-23 09:51 · Todo
Waste Transfer Note(s) for any tankering
☑ DONE as word doc - check date Service paperwork
2025-10-23 09:45 · Todo
☑ DONE as word doc - check date Service paperwork
Screenshot 2025-10-23 090423.png
2025-10-23 09:05 · Ruby Birks · Document
Screenshot 2025-10-23 090319.png
2025-10-23 09:03 · Ruby Birks · Document
IMG-20251003-WA0007.jpg
2025-10-16 09:25 · Ruby Birks · Document
IMG-20251003-WA0008.jpg
2025-10-16 09:25 · Ruby Birks · Document
IMG-20251003-WA0009.jpg
2025-10-16 09:25 · Ruby Birks · Document
IMG-20251003-WA0010.jpg
2025-10-16 09:25 · Ruby Birks · Document
Card Table
No mirrored card-table items yet.
Sync History
No sync history yet.