2026-02-27 13:04 · Todo
☑ Advise customer tank service is due - Installed w/c 11/08/2025
Richard Coomber STP Install - Pennine View, Brough Sowerby, Kirkby Stephen CA17 4EG, UK - 07481914484 - coomber.rm@gmail.com · Final Email to Building Control - Declaration from client & principal contractor - Pending client Declaration signage
2026-02-27 12:58 · Todo
Final Email to Building Control - Declaration from client & principal contractor - Pending client Declaration signage
2025-11-14 12:11 · Todo
Done - Tank Warranty Certificate
2025-11-12 10:18 · Todo
☑ Post installation visit - within 3 months - Installed w/c 11/08/2025
2025-11-07 10:53 · Todo
Done - Commission Certificate
2025-11-07 10:51 · Todo
Paid - Check payment of final bill, Invoice: 34514
2025-11-07 10:50 · Todo
☑ End of job call to installation lead / Improvement Review
2025-11-07 10:50 · Todo
☑ Update Tank Board as complete once final payment received
2025-11-07 10:50 · Todo
Done - Final email to ensure all has run well & Paperwork - Sent 12/09/2025
2025-11-07 10:50 · Todo
Done - Validate & complete Synchro ticket
2025-11-07 10:47 · Todo
N/A - 1) Call customer to check all is well
2025-11-07 10:47 · Todo
Done - Day 1 Engineer check in
2025-11-07 10:47 · Todo
Done - Call Shaun/Crutch to confirm everything is running smoothly
2025-11-07 10:47 · Todo
Done - Day 3, Message Customer
2025-11-07 10:47 · Todo
Done - Day 1, Message Customer
2025-11-07 10:47 · Todo
Done - Digger & Dumper etc. OFF HIRE
2025-10-23 09:51 · Ruby Birks · Document
2025-10-23 09:51 · Todo
Waste Transfer Note(s) for any tankering
2025-10-23 09:45 · Todo
☑ DONE as word doc - check date Service paperwork
2025-10-08 10:39 · Todo
N/A - Order Telemetry - where applicable
2025-10-08 10:39 · Todo
N/A - Order Ancillary Materials (pipework etc.)
2025-10-08 10:39 · Todo
Done - Order grab lorry/skip for spoil removal
2025-10-08 10:39 · Todo
Done - Order Tanker - Jetter
Richard Coomber STP Install - Pennine View, Brough Sowerby, Kirkby Stephen CA17 4EG, UK - 07481914484 - coomber.rm@gmail.com · Done - Order Treatment Tank - Add & allocate tank to Tank Board (if tank is located at Haigh) or Allocate tank to customer on Tank Board (if tank is located at MPC)
2025-10-08 10:39 · Todo
Done - Order Treatment Tank - Add & allocate tank to Tank Board (if tank is located at Haigh) or Allocate tank to customer on Tank Board (if tank is located at MPC)
2025-10-08 10:39 · Todo
Done - Order Concrete, Gravel & Other Bulk
2025-10-08 10:39 · Todo
Done - Make parts pack/Pick List
2025-10-08 10:39 · Todo
N/A - Permission to connect to Storm Drain
2025-10-08 10:39 · Todo
N/A - Section 106 application
2025-10-08 10:39 · Todo
N/A - Section 50 application
2025-10-08 10:39 · Todo
N/A - Environment Agency - Application
2025-10-08 10:39 · Todo
Done - Reviewing all project aspects with lead engineer
Richard Coomber STP Install - Pennine View, Brough Sowerby, Kirkby Stephen CA17 4EG, UK - 07481914484 - coomber.rm@gmail.com · Done - MPC Commissioning - ask Rob and arrange with Servicing team - if applicable
2025-10-08 10:39 · Todo
Done - MPC Commissioning - ask Rob and arrange with Servicing team - if applicable
2025-10-08 10:39 · Todo
Done - Handover info for lead
2025-10-08 10:39 · Todo
Done - Deposit Payment, Invoice:
2025-10-08 10:39 · Todo
Done - Final scope of works and sketches agreed with customer
2025-10-08 10:39 · Todo
Done - Search before you dig
2025-10-03 08:56 · Nikoleta Gouzopoulou · Document
2025-10-03 08:56 · Nikoleta Gouzopoulou · Document
2025-10-03 08:56 · Nikoleta Gouzopoulou · Document
2025-09-22 10:15 · Ruby Birks · Document
2025-09-22 10:12 · Todo
Done - Electrical Certificate from Paul Dean
2025-09-12 16:36 · Todo
Done - Book Digger, Dumper & Fuel
2025-09-12 16:36 · Todo
Done - Buildings Control Visit
2025-09-12 16:35 · Todo
Done - Update Tank Board once tank dispatched from Haigh or MPC
2025-09-12 16:32 · Nikoleta Gouzopoulou · Document
2025-09-12 16:30 · Nikoleta Gouzopoulou · Document
2025-09-12 16:26 · Nikoleta Gouzopoulou · Document
2025-09-12 16:26 · Nikoleta Gouzopoulou · Document
2025-09-12 15:15 · Todo
☑ Engineers list - Stock Taken
Richard Coomber STP Install - Pennine View, Brough Sowerby, Kirkby Stephen CA17 4EG, UK - 07481914484 - coomber.rm@gmail.com · Done - Book Ground-workers - Add Synchro ticket - SCs Invoice sent to Lee on 03/09/2025
2025-09-03 12:44 · Todo
Done - Book Ground-workers - Add Synchro ticket - SCs Invoice sent to Lee on 03/09/2025
2025-08-20 15:18 · Todo
- Day 5, Engineers daily call
2025-08-20 15:18 · Todo
- Day 4, Engineers daily call
2025-08-20 15:18 · Todo
- Day 3, Engineers daily call
2025-08-20 15:18 · Todo
- Day 2, Engineers daily call
2025-08-08 11:23 · Todo
Done - Check Sub-Contractors insurance (in date correct level of cover)
2025-08-08 11:18 · Todo
Done - Introduction email and confirmed date