Projects / RLX Construction (Ryan Spencer) - EMR Waste People, Saltley, Birmingham B8 1AP - Cesspit Install - 07891146477, ryan@rlxconstruction.co.uk
RLX Construction (Ryan Spencer) - EMR Waste People, Saltley, Birmingham B8 1AP - Cesspit Install - 07891146477, ryan@rlxconstruction.co.uk
Packaged Treatment Plant / Pump Station project
Summary
Open To-dos
58
Overdue
0
Upcoming Schedule
0
Recent Messages
0
To-do Lists + To-dos
Admin
• Done - Introduction email and confirmed date
• Done - Handover info for lead
• Done - Final scope of works and sketches agreed with customer
• N/A - Environment Agency - Application
• Paid - Deposit Payment, Invoice:
• Done - Search before you dig
• N/A - Permission to connect to Storm Drain
• N/A - Planning Application
Advanced Booking and Planning
• Check Sub-Contractors insurance (in date correct level of cover)
• Book Ground-workers - Add Synchro ticket
• Done - Book Digger, Dumper & Fuel
• Done - Order Cesspit
• Peagravel Done - Concrete pending confirmation - Order Concrete, Gravel & Other Bulk
• N/A - Book Electrician
• Done - Arrange Commissioning
• Done - Order Portaloo
On Site
• Done - Start Synchro ticket
• Done - Update Tank Board once tank dispatched from Haigh or MPC
• Booked - Buildings Control Visit
• Photos
• Done - Digger & Dumper etc. OFF HIRE
• Done - Speak to engineers to confirm all is well
• Done - Call customer to check all is well
• - Day 2, Engineers daily call
Post Install
• Done - Final Email to Building Control - Declaration from client & principal contractor
• Post installation visit - within 3 months
• Done - Update Tank Board as complete once final payment received
• N/A - Commission Certificate - to be retained until final balance is paid.
• N/A - Waste Transfer Note(s) for any tankering
• N/A - Advise customer tank service is due
• Snags
• Customer Feedback
Messages
No mirrored messages yet.
Schedule Entries
No mirrored schedule entries yet.
Documents
2025_09488_FP.pdf
Notice of Completion.pdf
AAI-Notification-of-Completion-v1.3.pdf
AAI-Notification-of-Completion-v1.3.pdf
Marsh-package-STP-Installation and Operation Manual.pdf
IMG-20250918-WA0013.jpg
IMG-20250918-WA0014.jpg
IMG-20250918-WA0015.jpg
IMG-20250918-WA0016.jpg
IMG-20250922-WA0050.jpg
IMG-20250922-WA0051.jpg
IMG-20250922-WA0052.jpg
IMG-20250922-WA0053.jpg
IMG-20250922-WA0054.jpg
IMG-20250922-WA0055.jpg
IMG-20250922-WA0056.jpg
IMG-20250922-WA0057.jpg
IMG-20250923-WA0001.jpg
IMG-20250923-WA0002.jpg
IMG-20250923-WA0003.jpg
IMG-20250923-WA0004.jpg
IMG-20250923-WA0005.jpg
IMG-20250923-WA0006.jpg
IMG-20250923-WA0007.jpg
IMG-20250923-WA0008.jpg
Recent Activity
Done - Final Email to Building Control - Declaration from client & principal contractor
Done - Final Email to Building Control - Declaration from client & principal contractor
Post Install
2025_09488_FP.pdf
Notice of Completion.pdf
AAI-Notification-of-Completion-v1.3.pdf
Post installation visit - within 3 months
Post installation visit - within 3 months
Check Sub-Contractors insurance (in date correct level of cover)
Check Sub-Contractors insurance (in date correct level of cover)
Advanced Booking and Planning
Book Ground-workers - Add Synchro ticket
Book Ground-workers - Add Synchro ticket
Done - Introduction email and confirmed date
Done - Introduction email and confirmed date
Admin
Done - Start Synchro ticket
Done - Start Synchro ticket
On Site
Done - Update Tank Board once tank dispatched from Haigh or MPC
Done - Update Tank Board once tank dispatched from Haigh or MPC
Done - Update Tank Board as complete once final payment received
Done - Update Tank Board as complete once final payment received
N/A - Waste Transfer Note(s) for any tankering
N/A - Waste Transfer Note(s) for any tankering
N/A - Service paperwork
N/A - Service paperwork
N/A - Advise customer tank service is due
N/A - Advise customer tank service is due
N/A - Commission Certificate - to be retained until final balance is paid.
N/A - Commission Certificate - to be retained until final balance is paid.
N/A - Electrical Certificate
N/A - Electrical Certificate
Snags
Snags
Customer Feedback
Customer Feedback
Paid - Payment of final bill - Invoice ST- 35091
Paid - Payment of final bill - Invoice ST- 35091
Done - Final email to ensure all has run well & Paperwork
Done - Final email to ensure all has run well & Paperwork
Done - Book Digger, Dumper & Fuel
Done - Book Digger, Dumper & Fuel
AAI-Notification-of-Completion-v1.3.pdf
Booked - Buildings Control Visit
Booked - Buildings Control Visit
Marsh-package-STP-Installation and Operation Manual.pdf
Done - Order Cesspit
Done - Order Cesspit
Peagravel Done - Concrete pending confirmation - Order Concrete, Gravel & Other Bulk
Peagravel Done - Concrete pending confirmation - Order Concrete, Gravel & Other Bulk
N/A - Book Electrician
N/A - Book Electrician
Done - Handover info for lead
Done - Handover info for lead
Done - Final scope of works and sketches agreed with customer
Done - Final scope of works and sketches agreed with customer
N/A - Permission to connect to Storm Drain
N/A - Permission to connect to Storm Drain
N/A - MPC Commissioning - ask Rob and arrange with Servicing team - if applicable
N/A - MPC Commissioning - ask Rob and arrange with Servicing team - if applicable
N/A - Section 106 application
N/A - Section 106 application
N/A - Section 50 application
N/A - Section 50 application
N/A - Environment Agency - Application
N/A - Environment Agency - Application
N/A - Planning Application
N/A - Planning Application
Done - Contract
Done - Contract