2026-01-20 13:27 · Todo
Done - Final Email to Building Control - Declaration from client & principal contractor
2025-12-04 12:35 · Todo
Post installation visit - within 3 months
2025-11-12 11:33 · Todo
Check Sub-Contractors insurance (in date correct level of cover)
2025-11-12 11:33 · Todo
Book Ground-workers - Add Synchro ticket
2025-11-12 11:32 · Todo
Done - Introduction email and confirmed date
2025-11-12 10:36 · Todo
Done - Update Tank Board once tank dispatched from Haigh or MPC
2025-11-12 10:35 · Todo
Done - Update Tank Board as complete once final payment received
2025-11-12 10:35 · Todo
N/A - Waste Transfer Note(s) for any tankering
2025-11-12 10:35 · Todo
N/A - Advise customer tank service is due
2025-11-12 10:35 · Todo
N/A - Commission Certificate - to be retained until final balance is paid.
2025-11-12 10:33 · Todo
Paid - Payment of final bill - Invoice ST- 35091
2025-11-12 10:33 · Todo
Done - Final email to ensure all has run well & Paperwork
2025-11-04 11:59 · Todo
Done - Book Digger, Dumper & Fuel
2025-10-16 15:36 · Todo
Booked - Buildings Control Visit
2025-10-09 11:53 · Ruby Birks · Document
2025-10-09 10:57 · Todo
Peagravel Done - Concrete pending confirmation - Order Concrete, Gravel & Other Bulk
2025-10-09 10:56 · Todo
Done - Final scope of works and sketches agreed with customer
2025-10-09 10:56 · Todo
N/A - Permission to connect to Storm Drain
2025-10-09 10:56 · Todo
N/A - MPC Commissioning - ask Rob and arrange with Servicing team - if applicable
2025-10-09 10:56 · Todo
N/A - Environment Agency - Application
2025-10-09 10:56 · Todo
Paid - Deposit Payment, Invoice:
2025-10-03 10:19 · Nikoleta Gouzopoulou · Document
2025-10-03 10:19 · Nikoleta Gouzopoulou · Document
2025-10-03 10:19 · Nikoleta Gouzopoulou · Document
2025-09-29 15:06 · Todo
End of job call to installation lead / Improvement Review
2025-09-29 15:05 · Todo
Done - Tank Warranty Certificate
2025-09-25 13:17 · Todo
Building Control - Acivico Building Consultancy - Submitted 15/09/2025
2025-09-25 11:15 · Todo
Done - Digger & Dumper etc. OFF HIRE
2025-09-24 17:20 · Todo
Done - Validate & complete Synchro ticket
2025-09-24 17:12 · Todo
Done - Speak to engineers to confirm all is well
2025-09-24 17:12 · Todo
Done - Call customer to check all is well
2025-09-24 17:10 · Ruby Birks · Document
2025-09-24 17:10 · Ruby Birks · Document
2025-09-24 17:10 · Ruby Birks · Document
2025-09-04 12:38 · Todo
☑ Make parts pack/Pick List - Sent & handed over to Michael 04/09/2025
2025-08-05 15:32 · Todo
Reviewing all project aspects with lead engineer
2025-08-05 15:15 · Todo
Order Telemetry - where applicable
2025-08-05 15:15 · Todo
Order grab lorry/skip for spoil removal
2025-08-05 15:15 · Todo
Order Ancillary Materials (pipework etc.)