Project Activity

Cross-project Basecamp activity feed for operational visibility.

Sync Admin
Hastoe, Dummetts - 1 & 2 Dummetts, Colyton Road, Southleigh, Colyton, Devon, EX24 6RL - Joe Maynard - 07876 835 543 - jmaynard@hastoe.com · Check payment of final bill, Invoice: 34269 - Commission certificate to be send to customer once final balance is paid
2026-01-06 09:36 · Todo
Check payment of final bill, Invoice: 34269 - Commission certificate to be send to customer once final balance is paid
2025-09-15 14:58 · Nikoleta Gouzopoulou · Document
2025-09-11 16:31 · Todo
☑ Final email to ensure all has run well & Paperwork
2025-09-04 12:25 · Nikoleta Gouzopoulou · Document
2025-09-04 12:20 · Nikoleta Gouzopoulou · Document
2025-09-04 12:20 · Nikoleta Gouzopoulou · Document
2025-09-04 12:20 · Nikoleta Gouzopoulou · Document
2025-09-04 12:20 · Nikoleta Gouzopoulou · Document
2025-09-04 12:20 · Nikoleta Gouzopoulou · Document
2025-09-04 12:20 · Nikoleta Gouzopoulou · Document
2025-09-04 12:20 · Nikoleta Gouzopoulou · Document
2025-09-04 12:20 · Nikoleta Gouzopoulou · Document
2025-09-04 12:20 · Nikoleta Gouzopoulou · Document
2025-09-04 12:20 · Nikoleta Gouzopoulou · Document
2025-09-04 12:20 · Nikoleta Gouzopoulou · Document
2025-09-04 12:20 · Nikoleta Gouzopoulou · Document
2025-09-04 12:15 · Todo
☑ Advise customer tank service is due - N/A
2025-09-04 12:15 · Todo
☑ Post installation visit - within 3 months - N/A
2025-09-04 12:15 · Todo
☑ Update Tank Board as complete once final payment received - N/A
2025-09-04 12:15 · Todo
☑ End of job call to installation lead / Improvement Review
Hastoe, Dummetts - 1 & 2 Dummetts, Colyton Road, Southleigh, Colyton, Devon, EX24 6RL - Joe Maynard - 07876 835 543 - jmaynard@hastoe.com · ☑ Final Email to Building Control - Declaration from client & principal contractor - N/A
2025-09-04 12:15 · Todo
☑ Final Email to Building Control - Declaration from client & principal contractor - N/A
2025-09-04 12:15 · Todo
☑ Electrical Certificate - N/A
2025-09-04 12:14 · Todo
☑ Commission Certificate - to be retained until final balance is paid - N/A
2025-09-04 12:14 · Todo
☑ Tank Warranty Certificate - N/A
2025-09-04 12:14 · Todo
☑ Engineers list - Stock Taken
2025-09-04 12:14 · Todo
☑ Waste Transfer Note(s) for any tankering - N/A
2025-09-04 12:14 · Todo
☑ Validate & complete Synchro ticket
2025-09-04 12:12 · Todo
☑ Make parts pack/Pick List - Handed over to Michael 11/07/2025
2025-09-04 12:12 · Nikoleta Gouzopoulou · Document
2025-09-04 12:11 · Todo
☑ Order Ancillary Materials (pipework etc.)
2025-09-04 12:10 · Nikoleta Gouzopoulou · Document
2025-09-04 12:10 · Nikoleta Gouzopoulou · Document
2025-09-04 12:05 · Todo
☑ Reviewing all project aspects with lead engineer
2025-09-04 12:05 · Todo
☑ MPC Commissioning - ask Rob and arrange with Servicing team - if applicable - N/A
2025-09-04 12:02 · Todo
☑ Search before you dig - Submitted 11/07/2025
2025-09-04 12:01 · Nikoleta Gouzopoulou · Document
2025-09-04 12:01 · Nikoleta Gouzopoulou · Document
2025-09-04 12:01 · Nikoleta Gouzopoulou · Document
2025-09-04 12:00 · Nikoleta Gouzopoulou · Document
2025-09-04 11:58 · Todo
☑ Order grab lorry/skip for spoil removal
2025-09-04 11:58 · Todo
☑ Deposit Payment, Invoice: 33471 - Remittance advise received 10/07/2025
2025-09-04 11:58 · Todo
☑ Survey / Site info - Joe Maynard attending site Tuesday 15/07/2025 1&2pm
2025-08-29 15:13 · Todo
☑ Book 6t Swivel Dumper - Morris Leslie, Exeter - 01392 422 993
2025-08-27 14:51 · Nikoleta Gouzopoulou · Document
2025-07-18 12:54 · Todo
☑ Book Ground-workers - Chris B. & Andy Lowe - Add Synchro ticket
2025-07-14 15:37 · Nikoleta Gouzopoulou · Document
2025-07-14 15:36 · Todo
☑ Introduction email and confirmed date - 14/07/2025
2025-07-14 15:35 · Todo
☑ Environment Agency - Application - N/A
2025-07-14 15:35 · Todo
☑ Section 50 application - N/A
2025-07-14 15:35 · Todo
☑ Section 106 application - N/A
2025-07-14 15:35 · Todo
☑ Permission to connect to Storm Drain - N/A
2025-07-14 15:35 · Todo
☑ Handover info for lead - 11/07/2025
2025-07-14 15:35 · Nikoleta Gouzopoulou · Document
2025-07-14 15:35 · Nikoleta Gouzopoulou · Document
2025-07-14 15:35 · Nikoleta Gouzopoulou · Document
2025-07-14 15:35 · Nikoleta Gouzopoulou · Document
2025-07-14 15:35 · Nikoleta Gouzopoulou · Document
2025-07-14 15:35 · Nikoleta Gouzopoulou · Document
2025-07-14 15:35 · Nikoleta Gouzopoulou · Document
2025-07-14 12:35 · Todo
☑ Final scope of works & sketches agreed with customer - 11/07/2025
2025-07-14 12:33 · Nikoleta Gouzopoulou · Document
2025-07-14 12:33 · Nikoleta Gouzopoulou · Document
2025-07-14 12:33 · Nikoleta Gouzopoulou · Document
2025-07-14 12:33 · Nikoleta Gouzopoulou · Document
2025-07-14 12:32 · Nikoleta Gouzopoulou · Document
2025-07-14 12:32 · Nikoleta Gouzopoulou · Document
2025-07-14 12:09 · Todo
☑ Start Synchro ticket - 14/07/2025
2025-07-14 10:26 · Nikoleta Gouzopoulou · Document
2025-07-14 10:20 · Todo
☑ Update Tank Board once tank dispatched from Haigh or MPC - N/A
2025-07-14 10:20 · Todo
☑ Check Sub-Contractors insurance (in date correct level of cover)
Hastoe, Dummetts - 1 & 2 Dummetts, Colyton Road, Southleigh, Colyton, Devon, EX24 6RL - Joe Maynard - 07876 835 543 - jmaynard@hastoe.com · ☑ Order Treatment Tank - Add & allocate tank to Tank Board (if tank is located at Haigh) or Allocate tank to customer on Tank Board (if tank is located at MPC) - N/A
2025-07-14 10:19 · Todo
☑ Order Treatment Tank - Add & allocate tank to Tank Board (if tank is located at Haigh) or Allocate tank to customer on Tank Board (if tank is located at MPC) - N/A
2025-07-14 10:18 · Todo
☑ Order Telemetry - where applicable - N/A
2025-07-14 10:18 · Todo
☑ Order Portaloo - Hirebase, 03456 460 169 - Tuesday 15/07/2025 AM - PO005226
2025-07-07 11:31 · Nikoleta Gouzopoulou · Document
2025-07-07 11:24 · Nikoleta Gouzopoulou · Document
2025-07-04 15:32 · Nikoleta Gouzopoulou · Document
2025-07-04 10:55 · Todo
Order Concrete, Gravel & Other Bulk
2025-07-04 10:54 · Todo
2) Call Chris B. & Andy Lowe to confirm everything is running smoothly
2025-07-04 10:54 · Todo
1) Call customer to check all is well