Jo Meakin - GreatOak Ltd, New House, Deanslade Farm, Claypit Lane, Lichfield WS14 0AG - joanna.m.butler@hotmail.com - 07837 703867 - INSTALLATION · Done - Advise customer tank service is due - Desludge details sent 04/11/24 Marsh 3800L Septic tank only - Property sold to Jodie Price 07712 118177 Jodie Price <Jodie.Price@hotel-latour.co.uk>
2025-09-30 10:10 · Todo
Done - Advise customer tank service is due - Desludge details sent 04/11/24 Marsh 3800L Septic tank only - Property sold to Jodie Price 07712 118177 Jodie Price
2025-01-22 14:07 · Todo
DONE - Buildings Control - Need to pay and book for Thursday 31/10
2025-01-22 14:07 · Todo
DONE CONCRETE NEED TO PAY - Order Concrete, Gravel & Other Bulk
2025-01-22 14:06 · Todo
SENT 05/12/24 Final Email to Building Control - Chased 20/01/25
2025-01-20 13:41 · Todo
DONE - Waste Transfer Note(s) for any tankering
2025-01-20 13:39 · Todo
DONE - Engineers list - Stock Taken
2025-01-20 13:38 · Louise Prince · Document
2025-01-20 13:38 · Louise Prince · Document
2025-01-20 13:37 · Todo
DONE - Call customer to check all is well - day one, day three and last day for final call
Jo Meakin - GreatOak Ltd, New House, Deanslade Farm, Claypit Lane, Lichfield WS14 0AG - joanna.m.butler@hotmail.com - 07837 703867 - INSTALLATION · DONE - Post installation visit - within 3 months - Installed W/C 28/10/24 Property now sold to Jodie Price 07712 118177 Jodie Price <Jodie.Price@hotel-latour.co.uk> - - Dean to carry out post install checks on 18/12/24
2024-12-18 08:54 · Todo
DONE - Post installation visit - within 3 months - Installed W/C 28/10/24 Property now sold to Jodie Price 07712 118177 Jodie Price - - Dean to carry out post install checks on 18/12/24
2024-12-16 11:52 · Todo
DONE - Commission Certificate - to be retained until final balance is paid.
2024-12-16 10:49 · Todo
PAID 14/12/24 Check payment of final bill
2024-11-04 14:23 · Todo
DONE - Final email to ensure all has run well & Paperwork
2024-11-01 09:39 · Todo
DONE - Digger & Dumper etc. OFF HIRE
2024-10-25 15:36 · Todo
N/A Permission to connect to Storm Drain
2024-10-25 15:36 · Todo
N/A Environment Agency - Application
2024-10-25 15:36 · Todo
N/A Order Control Panel - Telemetry - where applicable
2024-10-25 15:36 · Todo
N/A Order Ancillary Materials (pipework etc.)
2024-10-25 15:35 · Todo
DONE - Final scope of works and sketches agreed with customer
2024-10-24 15:11 · Todo
DONE - Order grab lorry/skip for spoil removal
2024-10-22 10:27 · Todo
DONE - Make parts pack/Pick List Given to Martin 22/10/24
2024-10-22 10:26 · Todo
N/A - Check Sub-Contractors insurance (in date correct level of cover)
2024-10-22 10:26 · Todo
DONE - Book Ground-workers Dean & Alex 28/10/24
2024-10-16 11:57 · Todo
DONE 16/10/24 Order Treatment Tank / Pump Station etc
2024-10-02 12:03 · Todo
DONE - Introduction email and confirmed date
2024-10-02 10:19 · Todo
End of job call to installation lead / Improvement Review